razorpay₹65.00 LPA· iit-d · sde-1google₹54.00 LPA· iiit-h · swe-imicrosoft₹49.50 LPA· iit-b · sdeatlassian₹38.00 LPA· nit-w · sde-1amazon₹44.20 LPA· bits-p · sde-1uber₹42.00 LPA· iit-kgp · sde-1razorpay₹65.00 LPA· iit-d · sde-1google₹54.00 LPA· iiit-h · swe-imicrosoft₹49.50 LPA· iit-b · sdeatlassian₹38.00 LPA· nit-w · sde-1amazon₹44.20 LPA· bits-p · sde-1uber₹42.00 LPA· iit-kgp · sde-1

Pipes AND Cisterns FOR Placement

11 min read
Topics & Practice
Last Updated: 1 May 2026
Reviewed by PapersAdda Editorial

Meta Description: Master Pipes & Cisterns for 2026 placement drives. Learn formulas, leak tricks & 23 solved TCS, Infosys, Wipro questions to ace your quantitative aptitude.

Introduction

Pipes and Cisterns is a high-yield quantitative aptitude topic that appears consistently in campus placement drives across IT, consulting, and core engineering companies. It is essentially an applied extension of the Time & Work concept, but with a fluid/tank context that tests your ability to handle positive (filling) and negative (emptying) rates simultaneously. In 2026 placement cycles, candidates can expect 1 to 3 questions per exam, typically carrying a weightage of 2-4% of the quantitative section. Major recruiters like TCS NQT, Infosys, Wipro, Accenture, and Cognizant frequently include this topic to evaluate logical reasoning, rate conversion skills, and accuracy under time pressure. Whether it’s calculating combined filling times, determining leak drainage rates, or solving partial-work scenarios, mastering Pipes and Cisterns gives you a decisive edge in clearing the aptitude cutoff. This guide by PapersAdda covers every sub-topic, provides 23 fully solved problems, and equips you with company-level shortcuts for 2026.

Key Formulas & Concepts

Understanding the rate-based approach is crucial. Treat the cistern/tank capacity as 1 unit or LCM of given times for faster computation.

1. Filling Pipe Rate:
If a pipe fills a tank in x hours, its filling rate = 1/x tank per hour.

2. Emptying Pipe Rate:
If a pipe empties a tank in y hours, its emptying rate = 1/y tank per hour (negative work).

3. Combined Work Rate:
When multiple pipes operate together:
Net Rate = (Sum of filling rates) − (Sum of emptying rates)
Time to fill/empty = 1 / |Net Rate|

4. Leak Impact Formula:
If a pipe fills a tank in x hours alone, but takes y hours due to a leak (y > x):
Leak Rate = 1/x − 1/y
Time taken by leak alone to empty full tank = 1 / Leak Rate = (x × y) / (y − x)

5. Partial Work & Time Relation:
Work Done = Rate × Time
Remaining Work = 1 − Work Done
Time to finish remaining work = Remaining Work / Active Rate

6. Alternating Pipes:
When pipes open alternately (e.g., A for 1 hr, B for 1 hr), calculate work in 2-hour cycles, find full cycles, then handle the remaining fraction.

Solved Examples (Basic Level)

1. A pipe fills a tank in 8 hours. What fraction of the tank is filled in 1.5 hours?
Solution: Rate = 1/8 per hour. In 1.5 hrs = 3/2 hrs, Work = (1/8) × (3/2) = 3/16.

2. Pipe A fills a cistern in 12 hours and Pipe B in 15 hours. How long will they take if opened together?
Solution: Combined rate = 1/12 + 1/15 = (5+4)/60 = 9/60 = 3/20 per hour. Time = 1 ÷ (3/20) = 20/3 = 6 hrs 40 mins.

3. A tap fills a tank in 10 hours, but a leak empties it in 20 hours. If both are open, how long to fill?
Solution: Net rate = 1/10 − 1/20 = (2−1)/20 = 1/20 per hour. Time = 20 hours.

4. Pipe P fills a tank in 6 hours. Due to a leak, it takes 9 hours. How long will the leak take to empty the full tank?
Solution: Leak rate = 1/6 − 1/9 = (3−2)/18 = 1/18. Time for leak alone = 18 hours.

5. A cistern is 1/4 full. Pipe X fills it in 5 hours. How much more time to fill completely?
Solution: Remaining work = 1 − 1/4 = 3/4. Rate = 1/5. Time = (3/4) ÷ (1/5) = 15/4 = 3.75 hours = 3 hrs 45 mins.

Practice Questions (Medium Level)

6. Two pipes A (10h) and B (15h) fill a tank. A third pipe C (20h) empties it. If all open together, find fill time.
Solution: Net rate = 1/10 + 1/15 − 1/20 = (6+4−3)/60 = 7/60. Time = 60/7 ≈ 8.57 hours.

7. Pipe X fills in 12h. Pipe Y fills in 16h. Both open for 4h, then X is closed. How long more for Y to finish?
Solution: Combined 4h work = 4×(1/12+1/16) = 4×(7/48) = 7/12. Remaining = 5/12. Y’s rate = 1/16. Time = (5/12)÷(1/16) = 20/3 = 6.67 hours.

8. A cistern has a leak that drains 50 liters/hr. A pipe fills it in 4 hours, but with leak takes 6 hours. Find capacity.
Solution: Leak empties in T = 1/(1/4−1/6) = 12 hours. Capacity = 12 × 50 = 600 liters.

9. Pipes A(8h), B(10h), C(12h) open together for 2 hours. A is closed. How much more time to fill?
Solution: 2h work = 2×(1/8+1/10+1/12) = 2×(44/120) = 11/15. Remaining = 4/15. B+C rate = 1/10+1/12 = 11/60. Time = (4/15)÷(11/60) = 16/11 ≈ 1.45 hours.

10. Pipe A is twice as fast as B. Together they fill in 18 hours. Find individual times.
Solution: Let B = x hrs, A = x/2. 1/x + 2/x = 3/x = 1/18 → x = 54. B = 54h, A = 27h.

11. A tap fills 1/3 tank in 2 hours. Another empties 1/4 tank in 1.5 hours. Both open, find net fill time.
Solution: Fill rate = (1/3)/2 = 1/6. Empty rate = (1/4)/1.5 = 1/6. Net rate = 0. Tank never fills (or stays constant).

12. Three pipes: A(15h), B(20h), C(30h). A opens at 8 AM, B at 9 AM, C at 10 AM. When is it full?
Solution: 8-9 AM: A does 1/15. 9-10 AM: A+B do 1/15+1/20=7/60. Total by 10 AM = 4/60+7/60=11/60. Remaining=49/60. All 3 rate = 1/15+1/20+1/30=13/60. Time=(49/60)/(13/60)=49/13≈3.77h=3h46m. Full at 1:46 PM.

13. Pipe P fills 40L/min. Pipe Q empties 30L/min. Tank capacity 2400L. Both open, time to fill?
Solution: Net = 10 L/min. Time = 2400/10 = 240 mins = 4 hours.

Advanced Questions

14. A cistern has two filling pipes (A: 12h, B: 18h) and one leak. With leak, it fills in 10h. Find leak’s emptying time.
Solution: Combined fill = 1/12+1/18=5/36. Net with leak = 1/10. Leak rate = 5/36−1/10= (25−18)/180=7/180. Time = 180/7 ≈ 25.71h.

15. Pipe A fills in 10h. After 4h, Pipe B (emptying, 15h) opens. How long more to fill?
Solution: Work done in 4h = 4/10=2/5. Remaining=3/5. Net rate=1/10−1/15=1/30. Time=(3/5)/(1/30)=18h.

16. Two pipes fill in 20h and 30h. Both open, but at 1/4 filled, a leak starts draining at 1/6 tank/h. Find total time.
Solution: Time to 1/4: Both rate=1/12. Time=(1/4)/(1/12)=3h. Remaining=3/4. New net=1/12−1/6=−1/12. Tank drains! Never fills. (Trick: leak > combined fill)

17. Pipe X fills 1/5 tank in 3h. Pipe Y empties 1/3 in 2h. Both open for 1h, then Y closed. Find remaining time for X.
Solution: X rate=1/15, Y rate=−1/6. 1h net=1/15−1/6=−1/10. Tank loses 1/10. Start=0, now=−1/10. X must fill 1+1/10=11/10. Time=(11/10)/(1/15)=16.5h.

18. A tank has inlet A(12h), inlet B(16h). Outlet C empties full tank in 24h. If all open, how long to fill 3/4 tank?
Solution: Net=1/12+1/16−1/24=(4+3−2)/48=5/48. Time for 3/4 = (3/4)/(5/48)=36/5=7.2h.

Common Mistakes to Avoid

Ignoring sign conventions: Emptying pipes must be subtracted, not added. Always assign negative rates to outlets/leaks.
Mixing rates and times: Never add hours directly (e.g., 10h + 15h ≠ 25h). Convert to fractions/LCM first.
Forgetting leak direction: A leak always increases filling time. If your calculated time decreases, you’ve added instead of subtracted.
Assuming linear work in alternating pipes: Alternating pipes create cycles. Calculate full cycles first, then handle the remainder separately.
Confusing capacity with rate: If liters/hour are given, find capacity first before switching to unit rates. Keep units consistent throughout.
Rounding too early: Fractions preserve accuracy. Convert to decimals/hours-minutes only in the final step.

Shortcut Tricks

1. LCM Efficiency Method: Take LCM of given hours as tank capacity. Convert each pipe’s rate to liters/hour. Add/subtract directly.
Example: A(6h), B(8h), C(12h empty). LCM=24L. A=4L/h, B=3L/h, C=−2L/h. Net=5L/h → 24/5=4.8h.

2. Direct Leak Formula: Leak Time = (Normal Time × Delayed Time) / (Delayed Time − Normal Time)
Example: 8h alone, 12h with leak → (8×12)/(12−8)=24h emptying time.

3. Two-Pipe Combined Shortcut: Time together = (A × B) / (A + B)
Example: 12h & 15h → (12×15)/(12+15)=180/27=20/3h. Works only for two filling pipes.

4. Partial Work Multiplier: If W work takes T time, remaining (1−W) takes T × (1−W)/W.
Example: 2/5 filled in 4h → Remaining 3/5 takes 4 × (3/5)/(2/5) = 6h.

Previous Year Questions

1. TCS NQT 2024: Pipe A fills in 20 min, B in 30 min. Both open. After 5 min, A closes. Total time?
Solution: LCM=60 units. A=3u/m, B=2u/m. 5 min work=5×(5)=25u. Remaining=35u. B alone=2u/m → 35/2=17.5 min. Total=22.5 min.

2. Infosys Campus 2023: A cistern fills in 12h. A leak at bottom empties it in 24h. Time to fill?
Solution: Net=1/12−1/24=1/24. Time=24 hours.

3. Wipro Elite 2024: Two taps fill in 10h & 15h. A leak drains 6L/h. With leak, fills in 18h. Find capacity.
Solution: Fill rate=1/10+1/15=1/6. Net with leak=1/18. Leak=1/6−1/18=1/9. 1/9 capacity=6L → Capacity=54L.

4. Accenture APAC 2025: Pipe P fills 1/3 in 4h. Pipe Q empties 1/2 in 5h. Both open 2h, then Q closed. Remaining time?
Solution: P=1/12, Q=−1/10. 2h net=2×(5−6)/60=−1/30. Tank loses 1/30. Need to fill 1+1/30=31/30. P alone: (31/30)/(1/12)=12.4h.

5. Cognizant GenC 2023: A(8h), B(12h), C(24h empty). Open together for 2h, then C closed. Total time?
Solution: Net=1/8+1/12−1/24= (3+2−1)/24=4/24=1/6. 2h work=1/3. Remaining=2/3. A+B=1/8+1/12=5/24. Time=(2/3)/(5/24)=16/5=3.2h. Total=5.2h.

Quick Revision

• Filling rate = 1/time, Emptying rate = −1/time
• Net rate = Σfill − Σempty
• Time = 1 / Net Rate
• Leak Time = (x·y)/(y−x) where x=normal, y=delayed
• Use LCM method for whole-number efficiency
• Negative net rate → tank never fills
• Convert partial work → remaining fraction → divide by active rate
• Always verify units (hours/minutes/liters) before computing
• TCS, Infosys, Wipro, Accenture prefer combined + leak + partial scenarios
• Practice 15-20 mixed questions before 2026 placement day


You May Also Like

Frequently Asked Questions

What is the salary range for placements that include Pipes & Cisterns in the aptitude rounds?

Salary outcomes vary by company and role, but Pipes & Cisterns is typically part of the Quantitative Aptitude section in early screening rounds. Candidates who perform well in these tests generally qualify for higher interview stages, which can lead to competitive offers in IT and consulting placements.

Who is eligible to attempt Pipes & Cisterns questions for placement exams 2026?

Pipes & Cisterns is suitable for most undergraduate students preparing for campus placements, especially those targeting IT, consulting, and core engineering roles. There’s no special eligibility beyond having basic algebra and ratio/speed-time understanding, since the topic relies on standard formulas and problem modeling.

How difficult is the Pipes & Cisterns section in placement exams?

The difficulty is usually moderate: straightforward single-pipe or two-pipe questions are common, while tougher sets involve leaks, alternating inflow/outflow, and time-dependent rates. With consistent practice, most candidates can reach a comfortable accuracy level because the underlying method (rate = work/time) remains the same.

What are the best preparation tips to master Pipes & Cisterns quickly?

Start by memorizing the core approach: convert each pipe’s flow into a rate, then use net rate to compute time. Practice with a mix of easy-to-hard questions daily, and focus on “setting up the equation” faster than doing lengthy calculations.

How many interview rounds typically include aptitude topics like Pipes & Cisterns?

Pipes & Cisterns is most commonly tested in written aptitude/online assessment rounds rather than later technical interviews. Many placement processes have an online test followed by technical rounds and HR rounds, where Quant aptitude is usually not repeated in the same form.

What common topics appear alongside Pipes & Cisterns in placement quantitative aptitude?

You’ll often see related time-work problems, mixtures & allegations, percentage and ratio, simplification, and basic algebraic equations. Many exams combine these topics in a single Quant section, so strengthening fundamentals helps you handle Pipes & Cisterns faster.

How do I apply for placement drives where Pipes & Cisterns is part of the selection test?

Typically, you apply through your college’s placement portal or the company’s campus recruitment page during the placement season. After applying, prepare for the online aptitude test using topic-wise practice sets like Pipes & Cisterns formulas, tricks, and solved problems.

What is the selection rate for candidates who prepare well for Pipes & Cisterns?

There isn’t a single public “selection rate” because it depends on company, batch size, and overall performance across all sections. However, strong Quant performance improves your chances of clearing the initial screening stage, which is often the biggest bottleneck in campus hiring.

Explore this topic cluster

More resources in Topics & Practice

Use the category hub to browse similar questions, exam patterns, salary guides, and preparation resources related to this topic.

Paid contributor programme

Sat this this year? Share your story, earn ₹500.

First-person experience reports help future candidates prep smarter. We pay verified contributors ₹500 via UPI per accepted story — with byline.

Submit your story →

Ready to practice?

Take a free timed mock test

Put what you learned into practice. Our mock tests match the 2026 pattern with timer, navigator, reveal, and score breakdown. No signup.

Start Free Mock Test →

More from PapersAdda

Share this guide: